« Home

Home » Law » Contract Law » Chen-Wishart: Contract Law 2e » Student resources » Guidance to textbook questions » Chapter 14

Chen-Wishart: Contract Law 2e

Chapter 14

1. To what extent, if any, is there room to award reliance damages, punitive damages, restitution, or account of profits for breach of contract?

See 14.2.1, 14.3 – 14.5.

This question invites you to consider the availability, and circumstances in which courts will award, damages measured other than by reference to the claimant's expectation. The issues you need to address include:

2. 'Monetary awards for breach of contract should do no more, and no less, than compensate the innocent party for his loss.' To what extent is this true? To what extent should it be true?

See 14.2.

This is essentially a re-run of question 1 with the focus on the derogation from the protection of the performance interest. What constitutes compensatable 'loss' under the expectation measure (see notes to question 3)?

3. What counts as 'loss' in the context of damages for breach of contract?

See 14.2.

The overriding question is the extent to which the law protects an innocent party's performance interest:

4. 'Contract law recognizes non-pecuniary loss reluctantly and only within narrow confines.' Discuss

See 14.2.4.

There is clearly an overlap here with question 3. The issues you should consider include:

5. 'In theory, the award of damages for breach of contract puts the claimant in the position he would have been in had the contract been performed. The reality falls far short of this.' Discuss.

See 14.2.

There is significant overlap between this question and question 3. The sub-issues to be considered include:

6. 'The protection of an innocent party's performance interest is merely one of the considerations that must be taken into account in assessing damages for breach.' To what extent is this true? What other considerations, if any, affect the amount of damages awarded?

See chapter 14.

This covers broadly the same ground as question 5, but with the emphasis on policy considerations discernible from the rules.

7. Ken employed Lou to install a new kitchen and add an extension to the living room: he paid Lou £30,000 on completion. Advise Ken on the following facts:

(a) Ken is very annoyed to find that the plasterwork in the extension has been painted a slightly different shade from that stipulated. Ken has rejected Lou's offer to redo the plasterwork for an extra £3,000 and hired Milo to redo the plasterwork for £6,000.

Has Lou breached the contract? If so, what damages would Ken seek? What are the arguments for and against Ken's claim? Does Ruxley v. Forsyth apply? Should Ken have accepted Lou's offer to redo the plasterwork?

(b) Completion is delayed, necessitating Ken and his family staying an extra month with Ken's in-laws in very cramped accommodations which caused great discomfort and distress all around. Moreover the delay meant that Ken had to pay £500 for an alternative venue for his friends wedding which he had offered to hold at his house.

Can Ken claim for his and his family's physical discomfort and distress? What about the cost of hiring a wedding venue? Is either loss too remote?

(c) After a few weeks, Lou's faulty wiring in the kitchen caused small sparks which ignited a gas leak that Ken had been meaning to fix for some time. The ensuing fire has caused £15,000 worth of damage to the kitchen.

Can Ken claim £15,000 for the damage to the kitchen? What of Ken's role in the fire?

(d) What difference would it make if Ken has not yet paid?

The question is then, whether Ken would be obliged to pay in circumstances (a) to (c) above. If payment is only due on completion then the entire obligations rule and the substantial completion exception apply. It will be a moot point whether (a) and (b) above would amount to substantial completion; (c) is a stronger case of non-substantial completion, allowing Ken to withhold payment. Spell out the alternative consequences. Would Lou be able to claim restitution for the work done?

8. Bugbusters won a major contract to clean 40 hospitals undertaking to meet 10 specified targets. Bugbusters instructed its workers to meet only six of the targets, saving £30,000 over six months. The hospitals are outraged when they learn of the breach, but it is impossible to prove whether any additional infections have resulted. Advise the hospitals.

There is a clear breach by Bugbusters. What damages can the hospitals claim when no provable loss has resulted? Specifically: